In England, give each existing tenant their EICR within 28 days of the inspection and complete required remedial or investigative work within 28 days starting with the inspection date, or sooner if the report requires it. After that work, send written confirmation with the original report to each existing tenant and the council within 28 days of completion, without waiting for a council request (regulation 3).

Those are separate tasks. Paying the electrician does not finish the paperwork, and receiving the PDF late does not restart the inspection clock. This guide is for private landlords in England, with sources checked on 13 November 2026.

What does an EICR C2 mean, and what happens next?

A C2 means potentially dangerous and requires remedial work; start by identifying the required action and its deadline. GOV.UK's report guidance distinguishes four codes:

  • C1: danger present, with risk of injury; the inspector may make it safe before leaving.
  • C2: potentially dangerous; remedial work is required.
  • C3: improvement recommended; this alone does not make a report unsatisfactory.
  • FI: further investigation required without delay; the current statutory follow-up duty still applies before the proposed change discussed below.

C1 and C2 mean an unsatisfactory installation. Read the overall assessment and required work rather than treating every observation as a repair order. Our EICR codes guide gives the fuller explanation; here the priority is what happens after the report arrives.

When does the EICR landlord 28 days clock start?

For required work, it starts with the inspection and testing date, not the report's delivery date or your acceptance of a quote. Regulation 3(4) specifies 28 days, or the shorter period in the report, starting with that date. Count the inspection date as day one.

Diary three entries immediately: the tenant-copy task, the work deadline and a follow-up to obtain completion evidence. Add the confirmation-sharing deadline when the work finishes. A booking is progress, but the duty concerns work carried out.

The next routine inspection is a separate date: regulation 3(2) allows no more than five years between inspections, with an earlier date controlling if required by the report. Use the actual next-inspection date rather than automatically adding five years.

Who needs a copy of the EICR?

Each existing tenant needs a copy, with separate rules for incoming tenants, prospective tenants and the council. Regulation 3(3) gives this checklist:

Recipient or recordWhat to do and when
Each existing tenantSupply the report within 28 days of the inspection and test
Any new tenantSupply the latest report before they occupy the property
A prospective tenant who asks in writingSupply the latest report within 28 days of receiving the request
Local housing authority requesting it in writingSupply the report within seven days of receiving the request
Your retained copyKeep it until the later of the next required inspection date and the actual next inspection, unless superseded by a newer report
Next inspectorSupply the retained report to the person carrying out the next inspection and test

The words each existing tenant matter for joint tenancies: make sure every joint tenant receives it. As a practical record, list each recipient and delivery date, rather than simply ticking “household informed”. The regulation does not prescribe a particular email template or require a separate email per person.

Must I send EICR remedial confirmation to the council?

Yes: where regulation 3(4) applies, send the original report and written confirmation to the local housing authority, as well as each existing tenant, within 28 days of completing the work. This is the automatic duty in regulation 3(5), separate from the seven-day response to a council request.

The qualified person's confirmation must establish that the work was done and either that the electrical safety standards are met or that further investigative or remedial work is required. Where investigation identifies more required work, regulation 3(6) repeats the work and confirmation process. An invoice saying “paid” does not establish those matters.

GOV.UK's remedial-work guidance accepts a satisfactory EICR, an Electrical Installation Certificate, a Minor Electrical Installation Works Certificate or other appropriate electrical certification. Check that the document actually confirms the required outcome.

Find the council's private rented housing or environmental health contact, identify the property and attach both documents. Keep the submitted files and delivery evidence together. One later GOV.UK paragraph mentions council confirmation “if requested”, but regulation 3(5)(c) imposes the automatic duty above, and the guidance's main checklist repeats it.

What does an illustrative EICR timeline look like?

It separates inspection, repairs and delivery, with the paperwork completed promptly after the work. This example is illustrative: the report records two C2s and one C3, with no shorter work period specified.

Date in 2026ActionClock or evidence
2 NovemberInspection and test completedDay one of the remedial period
4 NovemberOriginal report supplied to both joint tenantsTwo days after the test, within the tenant-copy period
10 NovemberQualified electrician completes the two C2 repairs and confirms standards are metEight days after the test; retain the confirmation
12 NovemberConfirmation and original report supplied to both tenants and the councilTwo days after completion, within the separate 28 days
29 NovemberOuter remedial deadline if the full period were needed2 November plus 27 days equals day 28

The C3 is recorded as an advisory improvement. It does not postpone the C2 repairs. This landlord finishes the sharing task ten days after inspection; there is no reason to wait until a deadline to send complete documents.

Can I use a different electrician or seek a second opinion?

You can use another qualified person for the required work: regulation 3(4), (5) and (8) requires competence, without reserving repairs to the original inspector. Give the replacement electrician the complete report and agree what completion evidence they will provide.

For a disputed code, ask the inspector to explain the observation and ask another qualified person for a documented technical opinion if needed. Keep both assessments. Seeking a second opinion does not itself suspend the statutory deadline or cancel the original findings.

Ask for a quote separating required work from advisory improvements. Our EICR cost guide covers inspection budgeting.

What changes for FI from 30 November 2026?

The published draft would remove the statutory FI follow-up duties for inspections completed from 30 November 2026, while preserving them for earlier inspections. On 13 November, legislation.gov.uk still labels the instrument as a draft that has not been made, so the change remains conditional.

Draft regulation 9 preserves the old duties for inspections completed before 30 November, even where the work happens later. For later inspections, if the draft takes effect, FI alone would no longer trigger regulations 3(4) and 3(5). The explanatory memorandum, paragraphs 5.2 to 5.4, says FI alone is not an unsatisfactory outcome under the updated standard. C1/C2 duties and the underlying safety duty remain. See our 30 November changes guide and recheck final legislation before applying the change.

What if a tenant refuses access for EICR remedial work?

Keep evidence of every reasonable step taken to arrange access and continue trying to resolve the obstacle. Regulation 3(2A), (2B) and (6A) provides protection for specified duties where the landlord can show all reasonable steps to comply.

Keep appointment offers, replies, cancellations and electrician correspondence. Where a tenant prevents entry, the landlord is not treated as failing to take all reasonable steps solely because they have not brought legal proceedings for access. That is not an automatic exemption for a missed appointment; obtain advice about the actual circumstances and any council notice.

Can an EICR breach lead to a £40,000 penalty?

Yes: regulation 11 permits financial penalties up to £40,000 for breaches of specified duties, where the council is satisfied beyond reasonable doubt. The private-landlord cap changed on 1 November 2025 under SI 2025/1043, regulations 1 and 10.

GOV.UK's electrical-safety guidance directs readers to different civil-penalty guidance for offences before and from 1 May 2026. That signposting does not make May 2026 the start of this electrical-safety cap: regulation 11 remains its specific basis. Do not assume the separate landlord fines starting-point table sets an EICR fine.

For specified non-urgent breaches, regulation 4 requires a council remedial notice. Its own 28 days starts with service; representations can suspend it. This does not give landlords permission to wait for enforcement before acting on an EICR.

What should I keep in the property's electrical-safety folder?

Keep the dated EICR, required-work list, completion confirmation and proof of who received each document and when. Add access correspondence, council requests, responses and the next-inspection date. Padlord can hold certificate dates and property documents; keep your delivery evidence alongside them.

Separate appliance records from installation reports. GOV.UK's additional equipment-checking regime concerns social landlords; private landlords must still ensure supplied appliances are safe. Do not treat an EICR as an appliance PAT record.

Use the compliance deadline checker for renewal planning, and keep these short work and document deadlines in your diary. Close the task only when the required work and the evidence-sharing are both complete.

General information as at 13 November 2026, not legal, financial or tax advice.

eicr landlord 28 dayswho needs a copy of the eicreicr remedial work 28 dayssend eicr to councileicr c2 what next